Check out our Hootie's Hardhat Updates at the bottom of this page, or we invite you to follow along on Social Media!

 

 

We are excited to share a campus update representing an important milestone for PHPS. After extensive research, discussions, and valuable input from our community, we have identified a new campus location for the 2025-2026 school year: 4000 McEwen Road, Dallas, TX 75244. Faculty and staff have visited the site and are already imagining what the space will become.

We look forward to welcoming new and returning families to the PHPS community in fall 2025. The admission process for the 2025-2026 school year will begin on November 1st. Please visit our Admission page to learn more, or reach out to our Director of Admission, Laura Holthouser at lholthouser@phps.org.

PHPS Admission


Bringing our Vision to Life!

We are shaping a bright future for PHPS student success through our new learning environment.

Our new interior floor plan includes spacious classrooms designed for our small-group learning model, allowing us to tailor each environment to meet the unique needs of our students. Additional features include a K-6 library center, modern technology and science labs, fine arts rooms, and outdoor play areas—all thoughtfully designed to enrich every child’s learning experience. We also have additional space to grow our program offerings, ensuring we can continue to meet the evolving needs of our students and community.

Interior Floor Plan

Exterior Site Plan

 

Here's a look at our exciting updates:

  • Ceilings Are Going In—Top to Bottom: Ceiling grid installation is nearly complete throughout both buildings, paving the way for final inspections early next week.
  • Let There Be Light: Light fixtures are being installed across the campus, with sleek linear lights for specialty ceilings arriving Monday to complete the look.
  • Fire Safety Systems Coming Online: Fire alarm boxes, sprinklers, and key components are being placed and connected—final safety systems are taking shape.
  • Airflow and Comfort, Locked In: HVAC is almost fully operational! Air grills and restroom exhaust fans are going in, and the last rooftop unit startup is scheduled for tomorrow.
  • Finishing Touches Underway: Millwork is complete, hardware is being installed, and the space is being prepped and protected as we wrap up interior details.
  • Walls, Windows, and Final Fixtures: Painting and wall prep are nearly done. Clerestory glass, restroom mirrors, and remaining door frame pieces are being measured, delivered, and installed in real time.
  • We’re getting closer every day—and it’s all coming together beautifully! Stay tuned for more updates as we move into the final stages of construction.

Click here to view the progress!

PHPS New Campus Update
4000 McEwen Road, Dallas, TX 75244


As we wind down for summer, don’t forget to check back in weekly for updates and follow our construction progress at 4000 McEwen. In this week’s communication, we want to highlight areas  at the new campus that will encourage collaboration and community for students and families. 


Cafeteria: Dining and Gathering Space
The new campus will have a spacious, dedicated cafeteria with large windows overlooking the playground and a fully functioning catering kitchen. Moving to a new property allows us to contract with a new caterer starting next school year.

New Caterer Starting Fall 2025: Spice of Life – After a thoughtful search, we are excited to welcome Spice of Life, a company that prides itself on healthy, made-from-scratch meals free of high fructose corn syrup, preservatives, and processed foods. Later this summer, you’ll receive more information about ordering lunch and viewing menus. Once school begins, we’ll also share who to contact with feedback or questions.

Multi-Use Functionality – This cafeteria space will also serve as an auditorium, complete with a retractable screen, speakers, a mounted projector, and a portable raised platform. Because we will not have a sanctuary, this space will be used for our weekly Tuesday chapel services. The order of service will remain the same, student birthdays will still be celebrated, and families are always welcome to attend. More details from the spiritual life team will be shared in August.

Inspiring New Library
We are sure you have heard how excited the teachers are for the new, large, bright, and inviting library designed to encourage student collaboration and community. The library has two walls of exterior windows and “storefront” windows in the hallway, plenty of soft seating, tables, and a reading nook. The space will feel open, engaging, and welcoming, a sure way to encourage shared reading experiences, book perusing, and a love of reading.

Gym and Storm Shelter
Our new gym/storm shelter will safely accommodate the entire school community and meet F5 tornado standards.

Multi-Purpose Gym – With 6,120 square feet, 23’ interior and 26' exterior walls, and ceiling height suitable for volleyball, the space will feature retractable basketball goals, bleachers, and locker rooms. It will host PE, sporting events, pep rallies, and assemblies. Designed to withstand wind speeds of 250 mph, the building is also equipped with separate emergency power and HVAC systems to ensure safety and comfort during extreme weather conditions. While some finish-out may occur after we move in, the gym will be fully usable when school opens in August 2025.

Thank you for your continued support and enthusiasm as we prepare for this exciting new chapter at PHPS. The new campus is more than just a building—it’s a reflection of our commitment to fostering a strong, connected, and inspired school community. We look forward to sharing more updates with you in the weeks ahead and can’t wait to welcome you to a space designed with our students and families at its heart.

Here’s what’s been happening around your future school this week – lots of exciting progress as we continue to shape a space where learning will soon come to life!

  • A Proud Walkthrough Moment: The PHPS School Board and administration toured the site this week — and they were thrilled! They saw firsthand how the spaces are transforming into the dream school they’ve envisioned.
  • Power and Safety Systems Progress: Electricians are wiring up panels and finishing rough-ins, while fire safety crews are pulling alarm wires and installing sprinkler lines. These hidden systems are key to making sure the school is safe, efficient, and future-ready.
  • Framing, Ceilings, and Doors: Inside, workers are framing clerestories, installing door frames, and setting up the ceiling grid — all the touches that turn open rooms into real learning spaces.
  • Walls and Interior Finishes: Crews are priming walls, taping, bedding, and patching — setting the stage for the next phase of interior finishes that will bring warmth and color to the school’s halls and classrooms.
  • Heating, Cooling, and Air Systems: Mechanical teams are starting up the rooftop units (RTUs), insulating ducts, and installing air filters to ensure the building will be cool in the summer, cozy in the winter, and healthy year-round.
  • Outdoor Cleanup and Prep: Workers are cutting grass, cleaning up the grounds, and installing water bags at trees to keep the site looking fresh and welcoming.

Click here to view our progress!

Hardworking Crews on Site
Over 80 dedicated workers are on site each day moving the project forward—from masonry teams laying block to specialists installing sprinkler systems.

Systems Taking Shape
Electrical wiring, mechanical units, and plumbing lines are nearly complete, bringing us one step closer to powering up and cooling down our new spaces.

Walls, Doors & Ceilings Coming Together
Ceiling grids are going up, door frames are being set, and wall finishing is well underway, making the inside of the building look more and more like home.

Passing Inspections & Staying on Track
Recent inspections, including mechanical and plumbing, have passed successfully, keeping our timeline strong and progress steady.

Improved Safety & Efficiency
The new sprinkler and fire safety systems, along with upgraded mechanical equipment, will make the building safer, more energy-efficient, and future-ready.

Preparing for Final Installations
Coming soon: light fixtures, catering space build-outs, and all of the finishes that will bring these exciting improvements to life.

Click here to see our progress!

Full Steam Ahead
Crews are moving efficiently with over 45 workers tackling key parts of the project. Every corner of the building is buzzing with progress.

Electric Energy
Major strides in electrical work—above-ceiling rough-ins are nearly done, and inspections are being passed like pros.

Pipes & Progress
Plumbing insulation is wrapping up, with top-out and framing inspections lined up to keep momentum strong.

Wall-to-Wall Action
Masonry, two-siding, one-siding, and patching—our teams are transforming frames into real rooms, one wall at a time.

Interior Upgrades
Tape and bedding is smoothing things out upstairs and down, prepping the way for the next stages of finishing work.

Looking Good
Not just building—beautifying! The grass is trimmed, and clean-up crews are keeping the site neat and organized.

Click here to see our progress!

 

Walls Are Taking Shape
Crews are making great progress installing and finishing walls on all floors. Many spaces now have both sides of the walls up—it’s really starting to look like a school!

Wiring for the Future
Electricians are hard at work running wires for lights, power, and technology. The second floor in the South Building is nearly finished with electrical work!

Pipes and Plumbing Progress
Plumbing teams are moving fast! They’re insulating pipes and extending vents all the way to the roof to get ready for sinks, restrooms, and more.

Air Systems Coming Together
Our HVAC crews are installing and insulating ducts that will help keep the buildings cool in summer and warm in winter. Restroom exhaust systems are also taking shape!

Brick by Brick
The Storm Shelter/Gym is taking shape. Masonry teams are laying concrete block walls and pouring grout. With 20 crew members on site, this work is moving right along!

Safety First
Low-voltage data teams are pulling wires for fire alarms, security, and data—helping make sure the school is safe, secure, and ready for all the tech our students will use!

Click here to see our progress!

Here’s what’s been happening around your future school this week – lots of exciting progress as we continue to shape a space where learning will soon come to life!

Wiring the Way Forward
Electricians have been hard at work across both buildings! We’ve made great strides with electrical systems in the ceilings and walls, and fire alarm, data, and security wiring is well underway. Everything’s on track to keep things safe and connected.

Plumbing Progress on Every Floor
Plumbing teams have been busy finishing top-out work on all floors. Inspections are rolling smoothly, and we're even preparing to button up walls in key areas now that those pipes are in place!

Walls That Work
From framing to insulating and adding drywall layers (“two-siding”), the walls are shaping up beautifully. North and South buildings are seeing major transformations as we prepare to tape and texture next!

Air Flow in Action
Mechanical crews have been running ductwork across both buildings—keeping airflow in check and ready for future comfort. Inspections have gone well, and revisions are being handled with care.

Courtyard Coming to Life
Over in the courtyard, new ADA ramps are being framed and poured—making sure our campus will be accessible and welcoming to all. It’s one more step toward a beautiful and inclusive space.

Safe & Secure
Fire sprinkler lines and alarms are being installed with precision. Safety comes first, and we’re proud to report that inspections have been passed and everything is moving forward as planned.

Click here to see our progress!

  • Building the Framework: Construction crews are hard at work framing walls on both floors. You’ll start to see classrooms and learning spaces truly take shape as the layout becomes more defined.
  • Wiring & Systems in Progress: Electricians, HVAC, and fire safety teams are installing essential systems, including ductwork, fire alarms, and ceiling wiring.
  • Network cabling begins next week: Which will lay the foundation for high-speed internet, classroom tech tools, and a fully connected campus.
  • Plumbing & Inspections: Water and drainage lines are being topped out and prepared for inspections. Teams are also backfilling plumbing trenches and securing everything to meet safety and city code requirements.
  • Interior Progress: With systems installed, crews are insulating walls and preparing for drywall and interior finishing. This step brings us closer to adding classroom features and educational spaces.
  • Cafeteria & Kitchen Construction: We are building a dedicated cafeteria and kitchen designed to meet city and health code standards.
  • Healthy, Flexible Meal Options: We will be partnering with a caterer committed to fresh, whole foods—free of artificial dyes, sweeteners, and high-fructose corn syrup. Meals will include fruits and vegetables daily, allergy-friendly options, and backup lunches for students who forget. Parents can still send lunch from home if they prefer.

Click here to see the progress!

  • Inspections & Approvals – Permits are in progress, and inspections for plumbing, electrical, and framing are scheduled throughout the week to keep the project moving forward.
  • Framing & Walls – Framing on the 2nd floor is actively progressing, with crews finalizing layouts and preparing for inspections before walls are enclosed early next week.
  • Electrical & Mechanical – Electricians are installing wiring and conducting wall rough-ins on both floors, while mechanical teams continue ductwork and system installations, with inspections taking place this week.
  • Plumbing – Plumbing on the 1st floor has passed underground inspections, allowing crews to backfill trenches. 2nd floor plumbing work, including drain and top-out installations, is nearing completion, with final inspections coming soon.
  • Flooring & Ceiling – Demolition of old wood flooring is wrapping up, and crews are cleaning open ceiling areas to prepare for further installations. New flooring and carpet work in stairwells is also underway.
  • Next Steps – Contractors will conduct a walkthrough to confirm all electrical, plumbing, and data requirements are met before walls are closed, ensuring all systems are properly placed.

Click here to see our progress!

PHPS Construction Project Update:



  • Plumbing & Electrical Work: Underground plumbing rough-in is progressing on both the North & South building 1st floors, with inspections scheduled. Electrical wall rough-in continuing, with inspections expected early next week.
  • Framing & Demo Progress: Framing and one-siding walls are underway on the North & South building 1st floors. North & South building 2nd floors are wrapping up demo and continuing the wall layout.
  • Mechanical Work: Duct rough-in is ongoing on the North & South building 1st floors, with insulation mockup completed. In the North & South building 2nd floors the crew is clearing out the remaining demo materials and stocking supplies.
  • Storm Shelter & Exterior Work: Prep work for the storm shelter is in progress, with rebar and exterior pad installation beginning. Crews are working on grade beams and tying rebar to support the next construction phases.
  • Onsite Coordination: Data, AV, and Security vendors have met with the construction team to coordinate and align installation plans.
  • Current Focus: Crews are prioritizing in-wall blocking for upper cabinets, restroom grab bars, and fixtures, ensuring smooth transitions to the next construction phases.
  • Overall Progress: Demo cleanup is nearly finished, framing and mechanical work continue, and teams are preparing for upcoming inspections and material installations.

Click here to see the progress!
 

PHPS Construction Project Update: Week of March 10th-14th

Exciting progress is being made on our campus improvements! Here’s what’s happening:

  • Electrical Work Advancing:
    Our electrical teams are making great strides, completing wall rough-ins on the 1st floors and demo work on the 2nd floors. These upgrades will ensure a safe and efficient system for our school.
  • Improved Airflow & Ventilation:
    Mechanical ductwork is progressing well on the 1st floors, while teams are wrapping up demo work on the 2nd floors. These improvements will enhance air quality and comfort throughout the building.
  • Stronger Spaces:
    Framing and wall work continue on the 1st floors, with great progress in both buildings. These updates will create sturdy and well-designed learning environments.
  • Plumbing & Flooring Preparation:
    Crews are working on underground plumbing, with trenching and drain installations underway. This work will support modernized restrooms and facilities for students and staff.
  • Collaboration & Planning:
    Our construction team held a successful meeting to coordinate the next phases of work, ensuring a smooth timeline. Moisture and material testing is also underway to maintain high-quality results.

Click here to see our progress!

PHPS Construction Project Update week of March 3rd-7th:
 

  • Plumbing & Mechanical Advancements – Plumbing rough-in is progressing in both buildings, while mechanical ductwork and demolition are moving forward across all floors.
  • Electrical Work on Track – Electrical demolition continues in both buildings, keeping the project on schedule.
  • Wall & Ceiling Progress – Concrete masonry and brick wall demolition is in full swing, with ceiling and wall grid removals making way for new installations.
  • Architectural Approval Secured – The wall layout for both buildings' first floors was reviewed and approved, allowing framing to begin as planned.
  • The building pad for the tornado storm shelter/gym is underway, progressing alongside the interior remodels.

Click here to see the progress!

  • North Building: The first floor’s wall and ceiling demolition is 75% complete! Next week, crews will begin work on the second floor.
  • South Building: The first floor’s new wall layout is finished, and electrical work is underway. Demolition for the second floor will begin next week, paving the way for exciting transformations!
  • Making Way for the Future: Concrete removal is in full swing in the parking lot area, clearing space for the sports field, playground, and storm shelter.
  • What’s Next? Next week, we kick off plumbing trench layouts in the South Building and continue prep of the North Building.

Click here to see our progress

 